Carbondale Road Bridge

Scope of Work

The bridge deck placement was executed without issue, consisting of 170 yd3 of concrete dosed at 4 lbs/yd3 of FiberForce 600. Placement proceeded at a consistent rate of 80 yds/hour. Fiber performance exceeded expectations—per QC Knife River, there were no occurrences of fiber balling or pump blockages throughout the duration of the pour, indicating excellent dispersion and pumpability.

  • Location

    Plymouth, CA

  • Date

    July 2025

  • Owner

  • Area

  • Volume

    170 yd3

  • Engineer

    CEIFCO

  • General Contractor

  • Concrete Contractor

  • Ready-Mix Concrete Supplier

    QC Knife River

  • Location

    Plymouth, CA

  • Date

    July 2025

  • Volume

    170 yd3

  • Engineer

    CEIFCO

  • Ready-Mix Concrete Supplier

    QC Knife River

Everything went really well, especially with the fibers. I don’t think we had a single ball at all. It was a great pour.

Austin Cordero

QC Knife River