Project Spotlight
Jiffy Lube
- FiberForce 300, FiberForce 750
- Slabs on Ground
- Retail
- Interior
Scope of Work
For this project, Resource Development Company, the concrete contractor, brought in FullForce to explore a conversion opportunity at this Jiffy Lube location with a focus on carbon reduction.
To meet the project’s sustainability goals, FullForce replaced rebar in the interior slabs with 5 lbs/yd³ of FiberForce 750 and further reduced the carbon footprint by dosing all exterior concrete with 1.5 lbs/yd³ of FiberForce 300.
-
Location
Sparks, NV
-
Date
December 2024
-
Owner
-
Area
-
Volume
600 yd3
-
Engineer
-
General Contractor
-
Concrete Contractor
Resource Development Company
-
Ready-Mix Concrete Supplier
American Ready-Mix
-
Location
Sparks, NV
-
Date
December 2024
-
Volume
600 yd3
-
Concrete Contractor
Resource Development Company
-
Ready-Mix Concrete Supplier
American Ready-Mix